Ivanpah Project: Green Light

ivanpah-project

The giant Ivanpah solar electric generating system (SEGS) in the California desert is more than 92 percent complete as BrightSource continues construction on the behemoth concentrating solar power (CSP) system, which generates electricity via a steam turbine. When complete its three towers will provide a combined 377 megawatts of solar generation for Southern California Edison and Pacific Gas & Electric under long-term power-purchase agreements.

When completed Ivanpah will be among the largest solar plants anywhere in the world. It will likely be the first major CSP system to come online in the US, although SolarReserve’s 110 megawatt (MW) Crescent Dunes Solar Energy Plant located near Tonopah, NV, also is slated for completion toward the end of 2013. Construction at that tower already is complete, as well. However, the SolarReserve system has an added component, thermal storage, which will allow it to provide power on par with base load power from a coal or natural gas-fired power plant.

Already BrightSource is testing the first unit with steam blows. It is prepping the second unit for steam blows as well, even as it continues to install heliostats at both the second and third units. The steam blows are an important step that allows the heliostats to focus sunlight on the tower and create steam, prior to connecting the system to a steam turbine. “During steam blows, upwards of thousands of heliostats are focused on the solar boiler to achieve the desired temperatures, pressures and flow rates,” the company says. It adds that the steam blows, which are part of building out any steam turbine generation system, clear debris inside the system pipes, as well as test system integrity and safety.

“Once the steam blows are complete, the team will remove the temporary steam blow piping and reconnect the piping to design conditions. The next step will be for the boiler to admit steam to the steam turbine,” BrightSource says. After the turbine is up and running it will be synchronized and connected to start generating electricity for the grid.

Overall, at the first tower, 96 percent of construction is complete, with all the heliostats in place. At the second Ivanpah tower, 92 percent of construction is completed, with more than 56,000 of the 60,000 heliostats are installed. The third unit at Ivanpah is a little further behind, but catching up quickly. There, more than 47,700 of the 60,000 solar heliostats are installed, between that and construction on the tower, the third unit is now about 89 percent complete.

Original Article on Solar Reviews

GO TO

Related posts

Top